Construction Progress ... 7/24/06
It's happening!  Teachers' belongings started being moved in today.


The first group of trucks started

unloading about 11:00 after picking up

teachers' materials at various sites.

Closed, and ready for another load

Waiting for teachers to arrive and

unpack.  Unpacking will begin soon ...

Entrance to Main Office

Looking into Main Office

Lights on in the Health Office

Mrs. Wardlow is ready to begin the year - almost.

Library Stacks

Outside MP Room

Inside MP Room

Computer Lab

One ESS classroom

Ess bathroooms

Kindergarten cubbies

Kindergarten bathrooms

Kindergarten class - left side ...

and right side across the front.

Kindergarten playground

Center of Campus

West Hall

East Hall

Hall out to Bus Circle

Bus Circle

Looking in to Campus from Bus Circle

Solar Panels

Playground Equipment ...

and more Playground Equipment

-The construction trailers are gone
-The fencing all around the outside is gone
-Buildings B, C, and D are all but finished
-Building E is almost there
-Building A still has some work to be completed - the Amphitheatre, MP room, lunch area, Ess, and offices are not finished - yet
-There is still some concrete to be poured, landscaping to be completed, and general clean-up to finish

The first day of Classes is August 24th - one month to go!