The Citizens' Oversight Committee
 is pleased to report
 that currently the
Building for Success Program
is on budget and
on schedule.

Contents:

Accomplishments in 2003
Program Timeline
Group One Project Status
2004 Expectations
Objectives & Challenges
Budget Overview
MAIN PAGE

Citizens' Oversight Committee Members:

Fred Sanford (Chair)
Todd Gutschow (Vice Chair) Andrew Berg
Chrissa Corday
Lee Dulgeroff
Kathy Frost
Tony Heinrichs
John Collins (COC Secretary/
  Deputy Superintendent)

Contact the Citizens’ Oversight Committee

Mailing Address:
Citizens’ Oversight Committee Poway Unified School District
13626 Twin Peaks Road
Poway, CA 92064-3034

Phone: 858-679-2622
email

Citizens’ Oversight Committee meetings are open to the public. Check the website for meeting times, minutes and agendas:

www.pusd.info/news/coc/

Websites:

Citizens' Oversight Committee:
www.pusd.info/news/coc/

Bond program and project information:
www.powayusd.com/bond

 


Current Building for Success Program Timeline


The following estimated timeline has been established to guide program progress.
The timeline for the 24 Poway Unified schools in the program will continue to be
updated as the program continues.

School Site Proposed
Start
Proposed Completion
Group One
Midland Elementary School Summer 2004 Winter 2005/2006
Westwood Elementary School Summer 2004 Winter 2005/2006
Mt Carmel High School   Summer 2004 Fall 2006
Poway High School   Summer 2004 Winter 2006
Group Two
Twin Peaks Middle School   Winter 2005 Winter 2006
Chaparral Elementary School   Spring 2006 Fall 2006
Garden Road   Summer 2006 Summer 2007
Painted Rock Elementary School   Summer 2006 Winter 2006/2007
Group Three
Black Mountain Middle School   Fall 2007 Fall 2008
Meadowbrook Middle School   Winter 2007 Winter 2008
Valley Elementary School   Winter 2007 Winter 2008
Los Penasquitos Elem. School Winter 2007 Winter 2008/2009
Pomerado Elementary School   Summer 2008 Spring 2009
Tierra Bonita Elementary School   Fall 2008 Fall 2009
Group Four
Canyon View Elementary School Spring 2009 Spring 2010
Rolling Hills Elementary School Summer 2009 Summer 2010
Sundance Elementary School   Summer 2009 Summer 2010
Abraxas High School   Spring 2009 Spring 2010
Group Five
Deer Canyon Elementary School Spring 2010 Winter 2010/2011
Morning Creek Elementary School Spring 2010 Winter 2010/2011
Sunset Hills Elementary School Summer 2010 Spring 2011
Turtleback Elementary School Summer 2010 Spring 2011
Bernardo Heights Middle School  Fall 2010 Summer 2011
Rancho Bernardo High School   Winter 2010 Spring 2012