| Rolling
Hills Elementary School |
Lunch Shelter Construction |
Prop C Construction Start Date : May 2008
Prop C Estimated Completion Date: February 2009 |
 |
Rolling Hills Elementary School
was built in 1978 |
| The Principal: Kathleen Marshack |
| Technology and playground improvements are complete. |
| Projects planned at Rolling Hills include: |
|
- Utility upgrade/efficiency improvements
- Renovate/upgrade restrooms as needed
- Modify/renovate library
- Modernize classrooms, such as lighting, power/data, flooring, and marker boards
- Renovate/expand staff work area
- Renovate/add computer laboratory
- ADA upgrades/compliance
|
- Food service expansion/renovation
- Site improvements for code and safety compliance
- Add/upgrade furniture and instrucitonal equipment
- Upgrade fire alarm systems
|
 |
| Accomplished in October |
- Bldg 7/Kitchen ceiling tile, doors/hardware, lighting, and Food Service Equipment
- Bldg 5 LRC/Classrooms Drywall, tack panels, Air Handlers, Doors/hardware, painting.
- SDG&E power to new switchgear
|
| Planned For November |
- Complete Kitchen
- New front entrance with concrete, posts & planters
- Bldg 5 – LRC HVAC start-up
- Bldg 5 Classrooms move in
- Bldg 1 Classroom demo
- Bldg 2 Classroom demo
|
| Please keep checking this website periodically for the latest news on our construction progress. |