| Pomerado
Elementary School |
Completed ADA Ramp |
Prop C Construction Start Date : November 2008
Prop C Estimated Completion Date: May 2009 |
 |
| Pomerado Elementary School was
built in 1960. |
| The Principal: Lisa Danzer |
| ADA Ramp Completed August 2008 |
| Projects planned at Pomerado include: |
- Utility upgrade/efficiency improvements
- Renovate/upgrade restrooms as needed
- Modify/expand/renovate library
- Modernize classrooms, such as lighting,
power/data, flooring, and marker boards
- Renovate/expand staff work area
- Add/renovate computer laboratory
|
- ADA upgrades/compliance
- Food service area expansion/renovation,
including new covered lunch area
- Site/playground improvements for
code and safety compliance
- Add/upgrade furniture and instructional
equipment
- Upgrade/replace communications and
fire alarm systems
|
 |
| Accomplished in October |
- Construction trailers, interim houses and connex boxes are on site.
- Layout for the temporary kitchen has been done.
|
| Planned for November |
- Re-route utilities, abate and demo existing kitchen, abate and demo building A, C, portables 23 and 24 (plumbing rough in).
- Re-route utilities and abate building B.
|
| Please keep checking this website periodically for the latest news on our construction progress. |