| Meadowbrook Middle School |
New Classrooms |
Construction Start Date:
June 2008
Estimated Completion Date: February 2009 |
 |
| Meadowbrook Middle School was built
in 1965. |
| The Principle: Cathy Brose |
| Projects planned at Meadowbrook: |
|
- Utility upgrade/efficiency improvements
- Add 12 new classrooms
- Add science laboratories
- New front entry trellis/Landscaping.
- Modernization: Admin/Classrooms #1 incl.
|
- Expand staff work area, Library, classrooms, computer lab, quiet reading area), Science Labs.
- ADA ramp upgrades, landscaping, technology, fire alarm, communication & utility upgrade/efficiency improvements.
|
 |
| Accomplished in October |
- Full occupancy of 900 Bldg.’s. Gas line at 911 & 912 complete.
- New front entry trellis - Demo, grading, layout, underground utilities, (elec./plumbing), dig footings & grade beams, set rebar for footings & templates, pour footings, set columns and begin canopy roof structure.
- Bldg. 7 Kitchen & Servery - Set food service equipment, complete flooring & interior finishes & prepare for occupancy. Health Dept. sign-off 10-23-08. Transition to new kitchen 10-24-thru 10-31.
- Bldg. 10 A/B Breezeway - Complete masonry block at base of columns, light fixtures & fire sprinklers.
- Removal of all leased relocatable bldg.’s & demolition of 4 remaining relo’s including restroom bldg.
- Landscaping between Bldg. 10 A/B & back side of Bldg. 9 complete.
|
| Planned for November |
- Bldg. 11 Choir - Begin survey, overex/reccompact, underground utilities, foundation & slab.
- Full occupancy of new production kitchen.
- Completion of new trash enclosure.
- Complete all railings for ADA ramp.
- Salvage of old food service equipment, abatement, demo of old kitchen, begin grading & footings for new lunch shelter.
- Complete new front entrance trellis.
- Continue landscaping, flatwork & asphalt.
|
| Please keep checking this website periodically for the latest news on construction progress. |
|
|
  |
|
|