Prop C Construction Start Date : May 2008
Prop C Estimated Completion Date: April 2009 |
 |
| Black Mountain Middle School was built in 1975. |
| The Principal: David Hall |
| Projects planned at Black Mountain include: |
|
- Utility upgrade/efficiency improvements
- Renovate/upgrade restrooms as needed
- Add classroom resource spaces and
classrooms for project growth
- Add science laboratories
- Expand/renovate library
- Renovate/expand staff work area
- Modernize classrooms/add resource
areas
- ADA upgrades/compliance
|
- Food service/lunch area expansion/renovation
- Site/grounds improvements for safety
compliance
- Add/upgrade furniture and instructional
equipment
- Upgrade/replace communications and
fire alarm systems
|
|
Accomplished in October |
- Parking lot seal coat
- Bldg 6 MPR/kitchen rough MEP, Stairs, Addn foundation,
- Bldg 6 Lunch Shelter erect steel columns, set roof trusses
- Bldg 9 Admin/Library framing, MEP rough, structural steel
- Bldg 10 New Classrooms framing, MEP rough, doors/windows, roofing
|
Planned For November |
- Pull 1/2 Electrical and Low Voltage to Bldgs 6, 9, 10
- Bldg 6 rough MEP, framing, FRP, drywall,
- Bldg 9, Aluminum storefront, plaster repair, insulation, drywall and begin painting
- Bldg 10 drywall and terrazzo
- Lunch Shelter metal decking skylights, roof sheathing, metal roofing, gutters/downspouts, electrical rough.
|